The North-South high-speed railway is expected to start construction at the end of 2028

The North-South high-speed railway project is entering the stage of preparing a feasibility study report with a contract implementation period of 30 months. According to the new roadmap, the consultant will complete the contents of alignment, technology, design and site clearance documents, aiming to start the project at the end of 2028.

The Thang Long Project Management Board under the Ministry of Construction has just approved the results of selecting a contractor to carry out a survey consulting package and prepare a feasibility study report for the North-South high-speed railway project. After the consulting unit was selected, the main implementation milestones of the project were also determined, with the contract implementation period lasting 30 months.

According to Mr. Nguyen Trung Son, Deputy Director of Thang Long Project Management Board, during the contract implementation process, the consulting partnership will have to complete four important milestones. By the third month, the consulting unit must propose a system of applicable standards and requirements as a basis for design, creating a foundation for implementing the next steps of survey, calculation and construction of technical plans.

By the 13th month, a mid-term report will be submitted, which focuses on proposing plans for selecting route directions, determining the location of control points and technological options. This is considered an important stage because these contents will shape the main technical solutions before the project enters the process of completing the feasibility study report.

KTX high-speed train in Korea. Image: KoreaRailway

According to the plan, by the 27th month, the feasibility study report will be submitted to the Appraisal Council and the Ministry of Construction for consideration. Three months later, the 30th month of the contract, the dossier is expected to be approved by the competent authority, completing one of the important preparatory steps before the project moves into the construction phase. In parallel with the reporting process, from the first quarter to the third quarter of 2027, the investor will direct the consulting unit and relevant parties to focus on surveying the terrain and geology along the entire route. Site clearance boundary documents are also prioritized for completion and early handover to localities to have a basis for implementing compensation, support and resettlement work right in 2027. With this progress, Thang Long Project Management Board aims to strive to start construction of the North-South high-speed railway at the end of 2028. The above timeline is given after the investment preparation plan is updated in accordance with the workload of survey, design, technology selection and completion of feasibility study documents of a particularly large-scale project. Previously, on November 20, Thang Long Project Management Board issued a decision approving the results of contractor selection for the TV-02 bidding package, including survey consulting work, feasibility study report preparation, FEED design and preparation of bidding documents. The Vietnamese – French – Korean contractor consortium won the contract with a value of more than 10,200 billion VND, implementation time of 30 months. The consortium includes four foreign contractors, of which France’s SYSTRA is the leading unit, and three Korean units including Sambo Engineering Co., Ltd, Yooshin Engineering Corporation and Korea National Railway. On the Vietnamese side, there is Transport Design Consulting Corporation – JSC, Southern Transport Design Consulting Joint Stock Company, Transport Investment and Construction Consulting Joint Stock Company and Hoang Long Construction Consulting Joint Stock Company. After the contractor selection results were approved, Thang Long Project Management Board invited the winning consortium to complete contract procedures. The signing ceremony is expected to be held at the end of November, thereby officially launching the survey, research and detailed design process for the North-South high-speed railway project. According to planning, the North-South high-speed railway has a length of about 1,541 km, connecting Ngoc Hoi station in Hanoi with Thu Thiem station in Ho Chi Minh City and passing through 15 provinces and cities. The route is invested in the form of a double track, using a gauge of 1,435 mm, a design speed of 350 km/h and a load of 22.5 tons per axle. Along the route, it is expected to arrange 23 passenger stations and 5 freight stations, creating a network connecting major economic and urban centers on the North – South axis. With a design speed of 350 km/h, the project is expected to form a new high-speed mode of transport, complementing the existing aviation, road and rail systems. Preliminary total investment of the project is about 67.34 billion USD. According to the plan, the feasibility study report will be prepared and approved in the period 2026-2028, while the basic goal of completing the entire project is set in 2035. Compared to the Government’s previous plan, which set the goal of starting construction at the end of 2026, the new schedule extends the preparation time to complete the survey, technology selection, design and site clearance. With the current roadmap, the end of 2028 is determined to be the target for project commencement, after feasibility study and investment preparation procedures are completed.

Chọn ngôn ngữ

You are accessing the website in Vietnamese language!
(Bạn đang truy cập website bằng ngôn ngữ Tiếng Việt!)

Select another language if you want to switch to
(Chọn ngôn ngữ khác nếu bạn muốn chuyển sang)